Shack Construction – Part 3/4 (Insulation, Drywall And Finish Construction)

Insulation and Vapor Barrier

Insulation And Vapor Barrier

The next step in our shack construction project was to install insulation and the associated vapor barrier. We also marked out the operating desk footprint with tape on the floor to get a better “feel” for the final configuration and ergonomics of the room. We then brought chairs into the room to ensure that we would have adequate room for both of us to “move around” within the shack. With these steps done, the drywall was installed and the taping and mud steps completed.

Drywall Work

Drywall Work

With these steps done, we installed a suspended ceiling in the room with provisions for recessed lighting. We took steps to limit the “drop” of the ceiling to only 4 1/2″ to ensure that we had plenty of ceiling to floor clearance in the final room.

Suspended Ceiling

Suspended Ceiling

Next, our electrician installed the lights in the ceiling which created better lighting in the room for the remaining finish work. The next part of the project was to install a hardwood floor in the room. We have used a Flooring System from Kährs in other parts of our basement and had excellent results with it so we decided to use the same system in our shack. The flooring “floats” on a pad that acts as a vapor barrier between to concrete floor and the hardwood. The resulting flooring is very durable and looks great. We also installed our Geochron lighted map at this point and finished all of our electrical boxes.

Hardwood Floor

Hardwood Floor

At this stage of the project, we turned the finish carpentry over to Jim and Bob Bourassa. They did an outstanding job with the moldings and other finish work.

Finish Carpentry Details

Finish Carpentry Details

They created some very nice custom details for our shack such as the finish molding around our cable conduits where they exit the walls by our operating positions.

Finished Cable Ducts

Finished Cable Ducts

Bob Bourassa built a support structure for the top of our operating desk and installed the associated cabinetry and end panels.

Operating Desk Frame

Operating Desk Frame

Next, Bob fabricated a custom top made from Corian Material and installed it. Note the openings in the back and corners for routing cables under the desk.

Completed Operating Desk

Completed Operating Desk

Bob also installed the storage cabinets and drawers and Brian, our electrician installed under cabinet lights to finish this area. We also installed the smoke and alarm system detectors in the room and integrated them into our alarm system.

Storage and Display Area

Storage And Display Area

The HVAC folks also completed the installation of the in-room A/C unit and heat pump.

In Room A/C & Heat Pump Unit

In-Room A/C And Heat Pump Unit

And finally, the door and associated moldings were installed.

Shack Door

Shack Door

We also put some work into finishing the area outside our shack. This shows the stairwell which leads from our shack to the rest of the house. Note how well the wall that we added to create the room has blended with the original first-floor wall by the stairwell. Again, Bob did a very nice job with the railing and tread molding in this area.

Stairwell from Shack to House

Stairwell From Shack To House

With all of these steps complete, our local building inspector paid us a final visit and gave us our occupancy permit which completed the construction phase of our shack. The final stage was to fit the room with all of the infrastructure and equipment to make our shack operational. This will be the subject of the next and final post in this series.

Are you interested in learning more about our shack design and construction? Here are some links with more information:

– Fred, AB1OC

Shack Construction – Part 2/4 (Electrical, HVAC, And Grounding)

20 KW Generator

20 KW Generator

We put considerable effort into planning the Electrical, HVAC and Grounding systems in our new shack. We have experienced some extended power outages in our area over the past several years and we had been planning to install an automatic generator system for some time. Given the electrical upgrades that we were doing in connection with the construction of our shack, we decided to install a 20 KW automatic generator system as part of the project. The generator also provides a good source of emergency power for our shack. We wanted to have enough fuel capacity to run our house off the electrical grid for a week and this required us to install a large underground propane talk.

Propane Tank for Generator

Propane Tank For Generator

The generator system includes an automatic transfer switch and load shedding system which will automatically start the generator when the power goes off as well as removing heavy loads like the range and air conditioning units should the generator’s capacity be exceeded.

Automatic Transfer Switch

Automatic Transfer Switch

We planned for a number of dedicated 120 VAC and 220 VAC circuits for each operating position in our new shack. These requirements plus the dedicated A/C unit for the room led us to install a separate sub-panel for the shack just outside the room.

Shack Breaker Panel

Shack Breaker Panel

The sizing of the shack’s A/C unit was based upon a heat calculation for the anticipated equipment that might be installed in the shack. As we learned from our experience with our temporary shack, its important to have a good cooling system as the heat that is generated from transceivers, computers, power amplifiers, etc. is considerable. The unit we choose is a heat pump system which can also provide heating should we ever need it during the winter months.

AC Outdoor Unit

A/C Outdoor Unit

We also installed a fresh air exchange system in the room to ensure good air quality during the expanded periods that we planned to be in the room.

Shack Ventilation System

Shack Ventilation System

The next step in this process was to rough-in the outlet boxes, power cabling, and HVAC ducts. We also installed low-voltage outlet boxes for Ethernet, Audio/Video services, satellite, cable, etc. connections to our Home Network.

A-V, Networking and Power

A-V, Networking, and Power

We installed a generous set of 120 VAC and 220 VAC outlet boxes at each of our two operating positions as well as at the planned equipment construction area. The picture below also shows the 2″ PVC conduits that we installed in the thicker standard 2″x6″ rear wall to allow us to route our feedlines and control cables from the ceiling to the floor of our shack.

Outlets by Operating Position

Outlets By Operating Position

The last element of this phase of the project was to build an RF Ground system and cable entry point for our shack. The first thing that we did was to drive a series of 8 ft copper ground rods outside our shack. Each of our two operating positions had three rods 6 ft apart bonded together in a star configuration.

RF Ground Rod

RF Ground Rod

Next, we drilled a small hole through the basement wall at each operating position and ran a heavy ground wire through the wall to the center of the underground rods. This created a very short, direct ground connection for each operating position. These holes were carefully sealed to prevent water leakage into the room.

Ground Entry in Shack

Ground Entry Into The Shack

Finally, we installed a ground block for mounting PolyPhaser Coaxial Lightning Protectors for our feedlines as they enter the shack. We also installed a section of 3″ PVC pipe to allow our feedlines to pass through the outside of the shack into the room. The 3″ PVC conduits in the ground by our shack entry lead to our existing antennas. We plan to install additional larger 6″ PVC conduits in the future to accommodate hardline feedlines to a future tower.

Cable Entry Outside Shack

Cable Entry Outside The Shack

With this stage of the project completed, we were ready for insulation, drywall, ceiling, and floor installation. These steps will be the subject of our next post.

Are you interested in learning more about our shack design and construction? Here are some links with more information:

– Fred, AB1OC

Shack Construction – Part 1/4 (Planning And Framing)

Our Temporary Station

Our Temporary Ham Shack

After becoming licensed in 2010/2011, AB1OC and AB1QB set up a “temporary” HF station in our second-floor home office. In retrospect, this was a good idea because it gave us a chance to use some of our HF equipment and learn what we really wanted to do with a more permanent station. Our temporary station did have a number of problems that eventually motivated us to build a more permanent “shack”. These included:

  • The second-floor location required a 20+ ft connection to the ground which created RF problems in the temporary shack
  • The room did not have adequate electrical power or cooling to allow full operation of our station in a comfortable environment
  • We did not have a good way to disconnect and ground our antennas during electrical storms
  • We only had room for one operating position which became a problem as we both got more involved in HAM radio

I plan to cover the design and construction of our new ham shack in a series of four posts. This first post will cover the planning and framing aspects of the project.

Late in 2011, we began to make plans for a more permanent station in the basement of our house. Our goals for our new ham shack design included:

  • Building a state-of-the-art multi-op station with separate positions that would allow both of us to operate at the same time
  • Adequate power and cooling to allow the use of legal limit amplifiers in a comfortable environment
  • Good lighting and ergonomics to support extended operating sessions including multi-day contests
  • A well-executed antenna switching and station ground system to provide better lightning protection and RF grounds for our station
  • Provision for full automation of our station’s antenna switching and human interfaces to support more automated sharing of our antenna farm in a multi-SO2R configuration
  • Addition of weak-signal VHF/UHF systems to our station
  • A permanent area for electronics construction and troubleshooting (we are both Electrical Engineers and are interested in the “home brewing” side of Amateur Radio)
  • An A/V area to allow us to take advantage of our existing Whole House Entertainment System
  • Adequate storage for all of our Amateur Radio items

The first step in the project was to secure a building permit to finish a room in our basement and clean out and seal the area prior to construction. Our basement is dry year-round so we could finish the shack area without water problems. As an extra precaution, we also installed underground drain lines on all of our rain spoutings that surround the shack area in our basement to ensure that we would not have water problems in the future.

Rain Drainage

Rain Drainage

With our building permit in hand, we translated our ham shack design to draw up detailed plans for the room’s framing, electrical system, and HVAC system, as well as plans for the finish elements such as the operating desk and cabinetry. The ARRL Amateur Radio Handbook is a good source of ideas and information for developing plans for a shack. We also put considerable time into planning the design of the shack’s grounding systems and cable entry. It’s important to think carefully about the final layout of the shack at this stage of the project and to carefully think through ergonomic issues like the location, height, and layout of the operating desk and associated seating and lighting.

Plans for our New Ham Shack Design

Plans For Our New Shack

In addition, we did careful heat dissipation calculations to determine the HVAC requirements for the room as well as electrical power planning to determine the total electrical capacity, circuit count, and individual circuit load requirements. We have been fortunate to work with several very good carpentry, electrical, and HVAC contractors on other remodeling projects that we have done around our home and these folks were very helpful in developing our plans for our new shack. Our contractors also handled some of the work to complete the project. We worked with Jim and Bob Bourassa (rwbjr@charter.net) on many of the carpentry aspects of our project. Brian Fessenden (fessendenbrian@yahoo.com), our electrician, helped us to plan and install the electrical and generator systems. Absolute Mechanical Systems, our HVAC contractor helped us with the HVAC systems in our Shack, and Brian Veillette (Nashyei@aol.com) handled the excavation and landscaping elements outside the shack.

With all of our plans done, we were ready to begin construction. We ordered all of the lumber needed for the framing and got our tools together.

Lumber for Framing

Lumber For Framing

One of the most useful tools at the framing stage of a project like this is a good set of laser levels. These tools help to get all of the walls and other aspects of the framing square, plumb, and level. Some time spent to get everything right at this stage makes the drywall, flooring, ceiling, and finish carpentry aspects go much more smoothly and ensures a good overall result.

Laser Levels

Laser Levels

The framing of our shack was a bit of a challenge due to several non-conventional aspects of our room and the plans for it. The following picture shows the nearly completed framing looking into the room. The back wall was thicker than standard to allow for the installation of 2″ PVC conduits to route coax and control cables inside this wall to the planned operating positions. The framed-out area on the back wall is a recess for a Geochron-lighted grey-line map. We also opted to finish the area around the outside window with a sloping window sill to maximize the natural light into the room.

Ham Shack Design - Shack Framing

Shack Framing (View Into The Room)

The picture below is a view of the framing from inside the shack. The stairs and the wall next to it also presented some challenges. The original width of the stairs did not allow the new wall to line up properly with the finished wall in the stairwell above the shack. To solve this problem, I had to remove the stair riser and narrow the stairs by about 1/2″. There also was a  column in the location of this wall to support the beam and floor above the shack so we had to temporarily support the wall with jack columns and build a load-bearing wall under this area. Finally, the overhead support beam and a series of HVAC ducts, and other lines between the beam and the front wall had the potential to create a low ceiling. Some careful attention to the framing in this area created a ceiling that was no lower than the bottom of the existing beam which allowed plenty of ceiling-to-floor clearance. These are all pretty standard framing construction problems and a good basement remodeling book will explain how to do these steps if they are needed.

Shack Framing 2

Shack Framing (View From Inside The Room)

We also opted to build an area outside the shack to mount a dedicated electrical breaker panel for the room as well as to provide a place to mount our planned antenna switching matrix. This was done by building a simple 2×4 frame on the wall and covering it with a piece of plywood. We call this “Node 1” as it is the second panel of this type in our basement. Node 0 holds our home Data and A/V network.

Ham Shack Design - Moutning for antenna switching and station equipment

Node 1

We installed a pair of bookshelves in this area to hold all of our Amateur Radio-related books and manuals. Our local Staples store supplied the shelves.

The next step of our shack construction project will be the electrical and HVAC rough-in. This will be the subject of our next post.

Are you interested in learning more about our ham shack design and construction? Here are some links with more information:

– Fred, AB1OC

First Tower Part 9 – Feedline Conduits And Electrical Power Complete

Conduits & Electrical at Tower

Conduits & Electrical at Tower

We made some more progress on our tower project today. Brian Veillette (Nashyei@aol.com), our excavation contractor, completed the conduits for our feedlines today and Brian Fessenden (fessendenbrian@yahoo.com), our Electrician, added an electrical outlet at the tower to provide power for our rotating ring and for general use at the base of the tower. We installed one 6″, one 4″ and two 2″ conduits to accommodate all of our hardline feed lines and control cables. These will allow us to run all of the cabling underground from the tower to our shack entry.

Conduits at Shack Entry

Conduits at Shack Entry

It will take a little time for our lawn to “heal” but it’s nice to have these steps completed. It looks like some of our four yagis may arrive as early as late next week and the next major step will be to assemble them.

You can read more about our tower project via the articles which follow:

– Fred, AB1OC

A Tour Of Our Shack

Our New Shack

I wanted to share a little more about our new shack, which was recently completed. Anita and I each have our own operating positions, which are SO2R capable. Anita’s setup consists of a Yaesu FTdx5000 and has provisions to add a second radio in the future. Fred’s position uses an Icom IC-7800 and an Icom IC-9100. Some of the key specifications and capabilities of our shack include:

  • A manual antenna switching matrix that allows us to connect any one of 6 antennas to our radios
  • W3QN bandpass filters systems for each radio to allow simultaneous operation of multiple transmitters at the same time on different bands
  • microHAM MK2R+ and SignalLink USB sound cards to enable digital mode operation
  • Dedicated displays and keyboards for the FTdx5000 ahttps://www.n1fd.org/2017/04/23/member-spotlight-ab1qb/nd IC-7800 radios to enable better use of their built-in Pan Adapters
  • Icom and Yaesu desk microphones and Heil ProSet headsets with boom microphones
  • Bencher paddle for CW
  • Windows 7 (64-bit) computers with dual monitors for running all manner of HAM software (we mainly use Ham Radio Deluxe at this time – more on software in a future post)
  • An Icom PW-1 Kilowatt Solid State Amplifier

The shack also has 125A of dedicated AC power, 70A of DC power, and its own Heat Pump system for heating and cooling. Our house also has a 20 KW automatic generator system that provides emergency power to the shack.

The following are a few pictures of our shack:

This is Fred's operating position.

AB1OC Position

This is Anita's operating position.

AB1QB Position

Our shack also has a dedicated area for equipment construction and test. It sure is nice to have a place where all of our test equipment, etc. can be left connected and set up for immediate use.

Electronic equipment for equipment construction and test.

Construction Area

Our shack includes areas for storage and an A-V area with a TV and entertainment audio. These are all essential items for a complete HAM-cave.

Storage and display area

Storage Area

TV and Entertainment Audio Equipment

A-V Area

Anita and I were able to use our new shack in its multi-op configuration for the 13 Colonies Special Event on the 4th of July. We were both on the air at the same time as K2K New Hampshire, and this was the first test of our station in a multi-operator configuration. One of us did SSB-phone on one band to avoid audio interference, while the other operated digital modes on a different band. For now, we built a matrix of manual antenna switches, allowing any of our four radios to use any available antennas. In the future, we plan to automate all of this with a microHAM system.

The work to construct our shack took about 8 months and was quite a bit of work. We started with an unfinished area of our basement, and we did the framing, electrical, HVAC, plumbing, drywall, ceiling, floor, and finish work. We had the help of several great contractors along the way. We plan to do a series of posts sometime in the future to explain a little more about what went into the construction of the room and the systems which support it.

[fvplayer id=”3″]

The video playlist above provides a “Virtual Station Tour” of our station.

Are you interested in learning more about our shack design and construction? Here are some links with more information:

– Fred, AB1OC

Welcome To Our Blog!

Our Shack

We are in the process of building a state of the art multi-operator Amateur Radio Station. We have created this blog to share our plans, experiences and learnings as we go. We hope that this information will be useful to other HAMs and potential HAMs that are thinking about building a station. Anita and Fred, the authors, are recently licensed Amateur Radio Operators and this is our first permanent station project. Our goals for our station are as follows:

  • A station that will operate and perform well on all HF bands and 6m as well as provide access to our local VHF and UHF repeaters
  • Support all modes of operation including SSB Phone, Digital and CW
  • Allow both of us to operate at the same time and also support Single Operator 2 Radio (SO2R) operations
  • Allow us to have fun working DX and contests
  • Be easily expandable for VHF/UHF weak signal work in the future

There are two parts to this project. The first is the construction of a permanent station in a dedicated, finished room in our basement and the second is to build a good antenna farm. As I write this, the station room is complete (see picture above) as is a basic part of the antenna farm. As time permits, we will add details and pictures of these parts of our project as well as the end result. The current work in progress in the construction of a new antenna system based upon a 100′ tower and an array of large yagi antennas as well as some new wire antennas which will be attached to the tower. Most of our early posts will likely focus on this area.

We welcome everyone’s thoughts and comments on our project via this blog. We hope that you enjoy the material that we are sharing here!

– Fred (AB1OC) and Anita (AB1QB)